Washing the House

After a week of wind and rain, where no work could happen outside, the sun came out on Saturday. Perfect weather for washing our house. Now all of the cement that was on the face of the bricks (from when the walls were built) is gone.

At the same time, the remaining damaged brick that we had asked to be replaced back in December was being replaced. The next step outside, is for the pointing to be done. Due to the storm, this could not be done, and therefore the scaffolding was not taken down on Friday as planned. utility connection has been put back by one week

As the scaffolding is in the way, the utility connection has been put back by one week to the week of 13th March.

Construction Dates

Begin (Groundwork)7th November 2016
End (Handover)19th April 2017