Interior Doors, Skirting Boards and Laminate Floor

Our interior doors and skirting boards on the ground-floor and the cellar are installed. One man arrived (completely on his own) on Thursday and installed 6 door frames (complete with hinges), then came back again on Friday and installed the skirting boards.

The doors are not hanging yet, as the adhesive that holds the door frames in place needs a day or two to completely set first. All we need to do is to lift the doors onto the lugs, in a few days time.

The first-floor doors and frames have not been installed yet (although it was originally planned that these would also be done).  It is simpler when this is done after the laminate floor is laid, so he will come back and do them another time.

On Friday, we started laying the laminate floor. The first room (bedroom) is now finished. Four rooms to go!

We will install the first-floor skirting boards, after the door frames are done.

Construction Dates

Begin (Groundwork)7th November 2016
End (Handover)19th April 2017