The House is Effectively Finished!
Friday again, and after further visits by the electricians, the decorators and the interior door guy over the past couple of days, we can now say that all work has effectively been completed.
Over this weekend, we are hoping get all of the skirting boards done on the first floor, and to install some temporary light bulbs in the rooms where the electricians haven't already done so.
There are still a couple of very minor things to be done. Silicone is not yet done in a couple of places, there is a little bit of painting to be finished here and there and the electricians still have not managed to correctly align the satellite dish, but that should all hopefully be done in the next few days, ahead of our ‘pre-delivery inspection meeting' on Wednesday.
Also during that meeting, the blower-door test will be carried out for our energy efficiency certificate, and the heating will be switched to heat-pump mode.
Solar Power: We still haven't had a really sunny day, but already the solar panels seem to be performing well compared to the assumptions we made some months back based on another installation in the area.
- Wednesday – 13.78 kWh
- Thursday – 7.04 kWh (Would have been higher, but was switched off from 10:15am to 1:45pm due to the electrician work)
- Friday – 9.68 kWh
We have now started a snag list of all the things that need to be finished / improved, but really up to now are impressed with the quality of most the work that Viebrockhaus and their contractors have done. We are also very impressed that they have pretty much kept on time throughout – as many things have been early as have been done late (which was anyway mostly due to icy weather).
The dust sheets that were covering most of the floor tiles downstairs have been removed today and on Monday or Tuesday a cleaning company (paid for by Viebrockhaus) is coming to do an initial cleaning. We will take some more photos after that, but for now here are some pre-cleaning photos…
We now have an appointment for our kitchen to be installed on 27th and 28th April (although they are apparently still waiting for some doors which might not arrive until slightly later).
Since we are eager to move in (and because we don't want to extend our holiday into the next week), we have changed the van hire to 25th and 26th April, and will probably now move in before the kitchen arrives. We can survive with a microwave and a kettle for a couple of days and we do also have a portable kitchen we could park outside the house if we really want to!
Construction Dates
Begin (Groundwork) | 7th November 2016 |
---|---|
End (Handover) | 19th April 2017 |