Roof Tiles – Part 2
This morning we had our weekly meeting with our Construction Manager. We didn't really have much to discuss with him, but we clarified a few details for the first weeks in the new year.
Work was well underway on the roof- the tiles were already off their pallet and laid out in small stacks ready for installation, and our Velux window had been fitted (it's on the other side, so you can't see it in the photo!)
We also noticed while taking this photo, that we can now see the south side of the house better. The skips are gone and the silo is gone. Only a few leftover bricks and the Viebrockhaus ashtray are still there (and, of course, the scaffolding!)
We're not sure if the roof will be completely finished today, but if not, it will be tomorrow. Hopefully, another photo will follow tomorrow evening.
After that, it is the Christmas holidays, so no further work is planned until Tuesday 10th January 2017.
Construction Dates
Begin (Groundwork) | 7th November 2016 |
---|---|
End (Handover) | 19th April 2017 |