The Heating is Running
Despite being cold outside, the house now has a warm feel to it. The heating system was started up for the first time on Wednesday.
Arriving in the morning, the plumbers were already filling up the system with water and getting the air out of the system.
The special program for drying the screed is running, and the system will automatically get progressively warmer over the next days.
While the system was filling up, the shower tray was being installed.
By Wednesday evening, we had received a delivery of lots of buckets of water. These were apparently for the plasterboarding for the ground floor (or at least for the skimming).
On Thursday morning, a delivery of plasterboard was just being offloaded from a small truck with a crane. By the evening, half of the ground floor has been plasterboarded…
Construction Dates
Begin (Groundwork) | 7th November 2016 |
---|---|
End (Handover) | 19th April 2017 |