Interior Construction Day 1

Today was the first day of interior construction, so we visited this morning to install a coffee machine for the workers, and leave some snacks for them.

When we visited again in the evening, the first thing we noticed when we went into the house this evening, was how warm it was. A 9 kW heater has been plugged in, and for the first time the house didn't feel so frosty. Thankfully this won't be running too long, as it must be spinning the electric meter quite quickly.

Already, the electrician has drilled holes for the electric sockets, light switches, thermostats, satellite TV connections and network cabling in all of the walls that are already there.

 

Unfortunately the kitchen work-top sockets, which are supposed to be at a height of 1.035m have been drilled at 1.35m, most likely he misread the plan. We've sent a mail to the construction manager this evening, and are hopeful that this will be quickly corrected.

The installation of the insulation upstairs has also been started.

 

Construction Dates

Begin (Groundwork)7th November 2016
End (Handover)19th April 2017