On Saturday, the pile of sand was mixed with cement and water by this machine, and pumped through a long hose into the house.





Once the pipes for the under floor heating were completely covered up, one of the builders moved from room to room on his knees, spreading the screed evenly across the floor.


The end result, the floors are now at the right level for the ceramic tiles / laminate to be laid.

First though, we must wait until Monday so that it has dried enough to walk on, and then several more weeks for all the moisture to have gone.


Construction Dates

Begin (Groundwork)7th November 2016
End (Handover)19th April 2017