Screed

On Saturday, the pile of sand was mixed with cement and water by this machine, and pumped through a long hose into the house.





Once the pipes for the under floor heating were completely covered up, one of the builders moved from room to room on his knees, spreading the screed evenly across the floor.


The end result, the floors are now at the right level for the ceramic tiles / laminate to be laid.

First though, we must wait until Monday so that it has dried enough to walk on, and then several more weeks for all the moisture to have gone.


Leave a Reply

Your email address will not be published. Required fields are marked *

nine + 20 =

This site uses Akismet to reduce spam. Learn how your comment data is processed.