The Scaffolding is Gone! (Again)

Since the pointing was finished on Saturday, the scaffolding has now been taken down again.

Unfortunately, the pictures were really grainy as they were taken at dusk.

Other than that, not much is happening at the moment.

We are visiting each day to ventilate the house so that the moisture can get out. The heating has now been running for almost three weeks, and the upstairs temperature has now reached 24.6° Celsius, and as you go up the stairs it really feels like entering a sauna.

In the coming days, the electrician should be back to install the sockets, and the digger should be coming back to dig a big hole for the 6600-litre rainwater tank and connect us up to the waste water and rain water drains. The painters should also be back to finish making the walls smooth and painting them.

 

Construction Dates

Begin (Groundwork)7th November 2016
End (Handover)19th April 2017